Gurney Creek Hydroelectric Project
Pitt Lake, British Columbia, Canada
Statistics:
 |
Turbine: One (1) double nozzle Turgo |
 |
Generator: 112kW @ 1200 RPM |
 |
Rated head: 60m |
 |
Rated flow: 0.26m3/sec |
 |
Commissioned: October 2025 |
In this project, an old crossflow turbine is replaced by a new and higher capacity Turgo turbine. The new turbine ultilises the available higher head that is not suitable for the crossflow turbine. The power upgrade is
much appreciated by the growing community.
|